Carnoustie Drive
Replacement of block paving where required and corrective works to levels of kerbs/drop kerbs etc on Carnoustie Drive. Work expected to be completed by 24 June.
Replacement of an existing underground drain pipeline near plots 152 and 162-165 (in the grassed area of the communal landscaped frontage) continue this week. Work will involve digging a trench to the extent of the underground pipework, breaking out the faulty pipework and replace with new. This will then be backfilled and re-landscaped afterwards. Work is expected to be completed by 10 June and during this period the area where work is taking place will be protected by heras panels and every effort will be made to keep any disruption to a minimum.
Work to reconfigure the gravel pathways that lead from The Fairway to the play area continues this week and is expected to last for approximately another week.